Liability and Delay Analysis & Expert Work.


Summary of major cases undertaken over last 3/4 years.

1. Contract :-           Government Housing Project Phase - 3# 35 storey blocks & 3 storey Primary School.
Contract Type :-     Hong Kong Government Housing Dept Conditions of Contract.
Client :-                     Nominated Specialist Sub-Contractor. (Respondent).
Work :-                    Arbitration Case. Defence and Counterclaims. Expert Witness for Liability – Planning & Extension
                                 of Time. Rebuttal of Claims for Delays to Main Contractor, Counterclaim for Delays to S-C's Works
                                  by MC and Recovery of Liquidated Damages unreasonably stopped.
Status :-                   Arbitrated Jan/Feb 1999, Award in favour of our Client. (Writer had left Hong Kong, sections of his
                                 work were used and relied on).

2. Contract :-           6 Kilometre Road Widening Contract, planned as 5# Phases each of 10/14 sections.
Contract Type :-     Hong Kong Government Civil Engineering Conditions of Contract
Client :-                     Main Contractor, (Claimant),via James R Knowles Hong Kong Limited.
Work :-                     Arbitration Case. Expert Witness for Liability – Planning and Extension of Time delays during the
                                 course of the works by others, (Utilities).
Status :-                   Completed Work handed back to Messrs James R Knowles. Arbitration, (Main Contractor
                                 v HK Government), initiated based on work done. Client successfully negotiated a settlement                                  prior to a hearing.

3. Contract :-           Residential & Commercial Complex comprising 5# 25 storey residential towers on a 5 level podium,
                                 (2# being underground)
Contract Type :-     Modified HKIA Contractor for Commercial Urban Development Complex.
Client :-                     Main Contractor (v Developer).
Work :-                     Litigation Work. Expert Witness for Liability – Planning and Acceleration. Rebuttal of Claim for Delay
                                 and Counterclaim for EoT due to delays by Developer and Acceleration to overcome imposed delays.
                                 All preparation work completed, full report given to client.
Status :-                   Litigation re-listed, change of legal representatives by client. No further work carried out.
                                 Client refused to acknowledge full fees.

4. Contract :-          Government Housing Phase comprising 5# 35 storey blocks and garage block.
Contract Type :-   Hong Kong Government Housing Dept Conditions of Contract.
Client :-                   Specialist Sub-Contractor, Claim and Defence against Counterclaim, in conjunction with Solicitor.
Work :-                   Arbitration Case. Expert Witness for Liability – Planning and Extension of Time. Formulation of
                                 Claims for delays to the S-C’s Works by M C and Rebuttal of Counterclaim for delays by S-C to
                                 M C's works and recovery of Liqidated Damages. Preparation work completed.
Status :-                  Arbitration cancelled, Main Contractor in Liquidation, Counsel for Claimant initially briefed.

5. Contract :-           Petrochemical Processing Plant, for Malaysian Owner.
Contract Type :-    Engineer, Procure and Construction Management, (EPCM).
Client :-                   Consultant Process Engineers.
Work :-                   Jointly as Planning Expert in conjunction with Claims Consultant to prepare :-
                                A major claim for delay and disruption, cost of delay and lost production and for accelerative
                                 measures instructed and taken during design and procure phases. Work completed to submission.
Status :-                  Successful negotiations concluded with the Owner thus avoiding further dispute.

6. Contract :-           MTRC (Mass Transit railway Corp’n, Hong Kong) Station Refurbishment Contract.
Contract Type ;-    Modified Standard MTRC Building Contract.
Client :-                   Main Contractor.
Work :-                   Planning Expert (prior to Expert Witness – if required later) to prepare the planning and liability
                                 points of claim in a claim against the MTRC for :-
                                 Delays and disruptions, cost of delays and lost production and establish the Extension of Time
                                 required.
Status :-                  Interim claims have been submitted as an initial basis for negotiation, main objective of avoiding
                                 Arbitration. The client issued a CoC without levying L D’s but no retention released. Further
                                 forensic work, claims submitted. Negotiated settlement Nov 2002, 16 month E o T & HK$35 of
                                42 Million claim agreed including retention.

7. Contract :-           Major landmark structure on Western Harbour Frontage, Hong Kong.
Contract Type :-    HKIA Standard form of Contract with modifications.
Client :-                   Specialist Nominated Subcontractor (Fire Services Installation), claimant
Work :-                   Planning Expert. Prepared a report on the planning and liability points of claim against the Main
                                 Contractor for :- Delays and disruptions, cost of delays and lost production and establish the
                                 extensions of time required.
Status :-                  Points of claim submitted, expert reports exchanged, expert meetings, hearing & Arbitrated.
                                 Award for client, L o E and costs

8. Contract :-           Residential Development, HK Housing Authority, Houses for Sale – Sandwich Class.
Contract Type :-    Hong Kong Housing Department Standard form of Contract.
Client :-                   Main Contractor.
Work :-                   Planning Specialist. Prepared and amalgamated details of delays and disruptions to establish
                                 times required and costs for EOT claims against the Client’s Architect & Consultants.
Status :-                  EOT Claims compiled, valued and submitted, E o T, L & E, variations negotiated.

9. Contract :-           Commercial Development, HK Housing Authority.
Contract Type :-    Hong Kong Housing Department Standard form of Contract.
Client :-                   Main Contractor.
Work :-                   Planning Specialist. Prepared, amalgamated details of delays and disruptions to establish times
                                 required and costs for EOT claims against the Client’s Architect & Consultants.
Status :-                  EOT Claims compiled, valued and submitted, E o T, L & E, & variations negotiated.

10. Contract :-         Kuala Lumpur International Airport. Steelwork for Main Terminal Building, Contact Piers,
                                 Bridges and Baggage Handling Systems.
Contract Type :-    In-House Form of Contract from S-C to cover Fabrication & Delivery, (by local sub-contractor).
Client :-                   Japanese Main Sub-Contractor - Supply & Erection of Structural Steelwork. (Claimant).
Work :-                   Expert Report on liability on points of claim. Claimant (Main S-C) claiming general damages for
                                 delays, disruptions in fabrication / delivery which affected the erection work.
Status :-                  Litigated in Singapore Court. Advised - award made in favour of client - submitted report used.

11. Contract :-         Involved 4# of 20# Power Stations in Massachusets and Texas, US of A – EPC Sub-Contract
                                 for Aftercoolers to Power Stations.
Contract Type :-    Swiss/German tailored contract for serial supply of Aftercoolers, by Main Contractor,
                                (Defendant).
Client :-                   Specialist German Manufacturer, Sub-Contractor for serial EPC S-contract, (Claimant).
Work :-                   Expert report on liability for points of claim for delays, disruptions, loss of production during
                                erection and EOT’s not awarded. (Almost no useful contemporary site records).
Status :-                  In arbitration, notices exchanged Arbitrator appointed, expert reports submitted and exchanged
                                with further meetings. Advised matter settled prior to tribunal hearing in favour of client with
                                costs to parties.

Additional General Remarks.
The above works have all involved :-
1. Extensive file research in existing and discovered contemporaneous contract files.
2. A large amount of programming work mainly using Primavera (P3) Software in standard, targeted and summary programs to illustrate various elements and effects in the course of and on the works.
3. The programming work has been supplemented by large amounts of spreadsheet data varying from quantative
take off (in item 2), to %age progress comparison tabulations and graphics and resource breakdowns and comparisons.